As part of the continuous effort to mitigate the adverse impacts posed by the pandemic on various economic sectors, Malaysian lawmakers have sought to amend the Temporary Measures for Reducing the Impact of Coronavirus Disease 2019 (COVID-19) Act 2020 (COVID-19 Act).
On 14 December 2021, the Temporary Measures for Reducing the Impact of Coronavirus Disease 2019 (COVID-19) (Amendment) Bill 2021 was tabled for its first reading before the House of Representatives of the Parliament. The Bill was passed without amendments after its second and third readings on 16 December 2021. The Senate subsequently passed the Bill on 22 December 2021. For the purpose of this update, the Bill is referred to as the Amendment Act.[1]
In relation to the Housing Development (Control and Licensing) Act 1966 (HDA 1966), s 5 of the Amendment Act seeks to insert a new Part XIA to the COVID-19 Act containing six new provisions, namely ss 38A to 38F.
Key takeaways
In essence, the new ss 38A to 38F revolve around the issues of late payment charges payable by purchaser in the event of late instalment payment, time for delivery of vacant possession (VP) / completion of common facilities by housing developer, and computation of defect liability period (DLP) under the prescribed
contract of sale in Schedules G, H, I and J of the Housing Development (Control and Licensing) Regulations 1989[2](SPAs).
The key takeaways from the six new provisions are as follows:
(a) Late payment charges
• For SPAs entered with developer before 31 May 2021, developer shall not impose late payment charges on purchasers for their unpaid instalment during 1 January 2021 to 31 December 2021 due to measures prescribed, made or taken under the Prevention and Control of Infectious Diseases Act 1988 (PCIDA 1988 Measures) – s 38B. This, on the face of it, appears to be an automatic entitlement granted to the purchasers.
(b) Time for delivery of VP/completion of common facilities
• For SPAs entered with developer before 31 May 2021, developer may apply to the Minister of Housing and Local Government (KPKT Minister) for any period from
1 January 2021 to 31 December 2021 (VP Relief Period) to be excluded from computing the time for delivery of VP or completion of common facilities of a housing accommodation – ss 38C(1) and (4).
• The KPKT Minister may grant such application if he/she is satisfied that the developer was unable to deliver VP or complete common facilities due to the PCIDA 1988 Measures; in such case, the VP Relief Period shall not be taken into account to compute the time for delivery of VP or completing common facilities and assessment of liquidated damages (LAD) in case of late delivery of VP/completion of common facilities – s 38C(2) and (5).
• The KPKT Minister, however, will not consider any application made after the expiry of time limit for delivery of VP/completion of common facilities stipulated in the SPAs – s 38C(3).
• Developer cannot invoke the usual deeming provision on delivery of VP if the purchaser, due to the PCIDA 1988 Measures, is unable to enter into possession or occupation of the property from the date of service of a notice to take VP during the period from 1 June 2021 to 31 October 2021 or any VP Relief Period granted by the KPKT Minister – s 38D.